Carrigaline, Co. Cork

Carrigaline, Co. Cork: wastewater treatment is rated green (spare capacity); 2 of the 4 nearest substations have spare demand capacity; 53 planning applications were lodged within about 3 km in the past year.

House prices

CarrigalineCo. Cork
0200k400k600k201720192021202320252026435k390k

Median sale price per year where there were 10+ sales; sales matched to Carrigaline from the address on the Property Price Register.

Water

Treatment plantCapacityUpgrade
Cork Lower Harbour WWTPGreen–

Nearest substations

SubstationDistanceSpare demand MVASpare generation MW
CARRIGALINE (166000) 38 kV STATION MV1 km0.03.0
KILMONEY (482000) 38 kV STATION MV1 km0.00.0
BARNAHELY (772000) 110 kV STATION 38 kV4 km20.524.4
BARNAHELY (772000) 110 kV STATION MV4 km18.258.0