Can it be built in Roscommon?
Water, electricity, planning and housing starts in Roscommon, from the operators' own registers.
In Roscommon, 1 of 31 settlements have no spare wastewater capacity and 3 have limited capacity; 2 of 6 substations show no spare demand capacity; 182 homes were started in the past 12 months (2.6 per 1,000 people).
Wastewater capacity
| Settlement | Plant | Capacity | Upgrade |
|---|---|---|---|
| Ballinameen | Ballinameen WWTP | Red | Yes |
| Castlerea | Castlerea WWTP | Amber | |
| Monksland (Athlone) | Monksland WWTP | Amber | |
| Roscommon | Roscommon WWTP | Amber | |
| Arigna | Arigna WWTP | Green | |
| Athleague | Athleague WWTP | Green | |
| Ballaghaderreen | Ballaghaderreen WWTP | Green | Yes |
| Ballinlough | Ballinlough | Green | |
| Ballintober | Ballintober WWTP | Green | |
| Ballyfarnon | Ballyfarnon WWTP | Green | |
| Ballyforan | Ballyforan WWTP | Green | |
| Bellanagare | Bellanagare WWTP | Green | |
| Boyle | Boyle WWTP | Green | |
| Cloonfad | Cloonfad WWTP | Green | |
| Cootehall | Cootehall WWTP | Green | |
| Cortober | Carrick‐on‐Shannon WWTP | Green | |
| Creagh WWTP | Creagh WWTP | Green | |
| Croghan | Croghan WWTP | Green | |
| Elphin | Elphin WWTP | Green | |
| Frenchpark | Frenchpark WWTP | Green | |
| Hodson Bay | Hodson Bay WWTP | Green | |
| Keadew | Keadew WWTP | Green | |
| Knockcroghery | Knockcroghery WWTP | Green | |
| Lanesborough-Ballyleague | Ballyleague WWTP | Green | |
| Lecarrow | Lecarrow WWTP | Green | |
| Lisacul | Lisacul WWTP | Green | |
| Loughlynn | Loughlynn WWTP | Green | |
| Roosky | Roosky WWTP | Green | |
| Strokestown | Strokestown WWTP | Green | |
| Termonbarry | Termonbarry WWTP | Green | |
| Tulsk | Tulsk WWTP | Green |
Electricity substations
| Substation | Class | Demand MVA | Gen MW |
|---|---|---|---|
| BALLAGHADERREEN (433000) 38 kV STATION | MV | 0.0 | 2.5 |
| ROSCOMMON (136000) 38 kV STATION | MV | 0.0 | 3.5 |
| BOYLE (047000) 38 kV STATION | MV | 1.0 | 0.0 |
| CASTLEREA (256000) 38 kV STATION | MV | 1.3 | 3.1 |
| GURTEEN (045000) 38 kV STATION | MV | 2.4 | 4.2 |
| TONROE (904000) 110 kV STATION | 38 kV | 6.1 | 7.9 |
Planning
Applications lodged in Roscommon, data to 21 Oct 2026. Median decision time 88 days.
By town (within ~3 km)
| Town | Applications (12m) | Homes granted | One-off houses |
|---|---|---|---|
| Roscommon | 39 | 4 | 4 |
| Castlerea | 20 | 1 | 2 |
| Boyle | 17 | 0 | 0 |
| Tarmonbarry | 16 | 0 | 1 |
| Cootehall | 14 | 1 | 3 |
| Athleague | 12 | 0 | 1 |
| Elphin | 11 | 0 | 0 |
| Strokestown | 11 | 1 | 0 |
| Ballaghadereen | 9 | 0 | 0 |
| Hodson Bay | 9 | 0 | 2 |
| Ballinlough | 7 | 2 | 0 |
| Keadew | 7 | 0 | 0 |
| Lecarrow | 7 | 0 | 2 |
| Bellanagare | 6 | 0 | 2 |
| Croghan | 6 | 2 | 2 |
| Frenchpark | 6 | 1 | 1 |
| Ballyforan | 5 | 1 | 1 |
| Knockcroghery | 5 | 2 | 2 |
| Lisacul | 5 | 2 | 1 |
| Ballyfarnon | 4 | 0 | 0 |
| Four Mile House | 4 | 0 | 0 |
| Roosky | 4 | 0 | 0 |
| Tulsk | 4 | 0 | 0 |
| Arigna | 3 | 0 | 0 |
| Cloonfad | 3 | 1 | 0 |
| Ballinameen | 2 | 0 | 0 |
Large schemes (50+ homes)
Permission for development which will consist of 52 no. dwellings comprising of 22 no. 4-bed semi-detached 2 & 1/2-storey, 3 no. 4-bed detached 2 & 1/2-storey, 12 no. 4-bed semi-detached 2-storey, 1 no. 4-bed terraced 2-storey, 1 no. 5-bed detached 2-storey, 4 no. 4-bed semi-detached, double aspect 2 & 1/2-storey, 1 no. 4-bed terraced, double aspect 2 & 1/2-storey, 8 no. 2-bed 2-storey duplex apar
Permission to demolish existing outbuilding, formerly serving a dwelling house, which had previously been demolished and to construct 99 No. dwelling units and a Creche facility. The development will consist of 6 No. 2 storey x 2 bed units (composed of 2 blocks x 3 No. units), 2 No. x 2 bed apartments over the Creche facility, 34 No. 2 storey x 3 bed semi-detached units, 36 No. 2 storey x 4 bed se
Housing starts
Public projects in Roscommon
| Project | Stage | Cost | Department |
|---|---|---|---|
| Boyle Primary Care Centre | 5. Post Completion Review and Benefits Realisation | – | Department of Health |
| Roscommon Rehabilitation Unit | 1. Strategic Assessment and Preliminary Business Case | – | Department of Health |
| Roscommon Sewerage Scheme | 5. Post Completion Review and Benefits Realisation | – | Uisce Éireann |
| An Chistin Project | 5. Post Completion Review and Benefits Realisation | – | Roscommon County Council |
| Boyle Regeneration - An Ríoga | 5. Post Completion Review and Benefits Realisation | – | Roscommon County Council |
| Life Sciences Innovation Hub and Soft Landing Space | 5. Post Completion Review and Benefits Realisation | – | Roscommon County Council |
| An Bealach Project | 5. Post Completion Review and Benefits Realisation | – | Roscommon Integrated Development Company Ltd |
| N5 Ballaghaderreen to Scramoge | 4. Implementation | – | Department of Transport |
| The Walk, Rosommon Town | 5. Post Completion Review and Benefits Realisation | – | Department of Housing, Local Government and Heritage |
| Meadowbrook, Ballyclare Rd., Ballyleague, Co. Roscommon | 5. Post Completion Review and Benefits Realisation | – | Department of Housing, Local Government and Heritage |
| Silveroe Meadows, Boyle | 5. Post Completion Review and Benefits Realisation | – | Department of Housing, Local Government and Heritage |
| Ballaghdereen Public Realm Enhancement | 4. Implementation | – | Roscommon County Council |
| Plunkett Community Nursing Unit, Boyle | 5. Post Completion Review and Benefits Realisation | – | Department of Health |
| Aras Mathair Pol Community Nursing Unit | 5. Post Completion Review and Benefits Realisation | – | Department of Health |
| Sacred Heart Hospital, Roscommon | 1. Strategic Assessment and Preliminary Business Case | – | Department of Health |
| Coláiste Chiaráin, Summerhill, Athlone, Co. Roscommon - 68325L | 5. Post Completion Review and Benefits Realisation | – | Department of Education |
| Energising Boyle Town Centre and King House | 4. Implementation | – | Roscommon County Council |
| Public Realm Plan - Market Square & Main Street - Market Square & Main Street | 4. Implementation | – | Roscommon County Council |
| Roscommon Town Centre | 5. Post Completion Review and Benefits Realisation | – | Roscommon County Council |
| Roscommon Town Putting the Spokes back into the Hub- Call 2 | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Roscommon County Council |
| DigiWest - Location #2 of 4 - Tulsk | 5. Post Completion Review and Benefits Realisation | – | Western Development Commission |
| Putting the Heart Into Monksland | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Roscommon County Council |
| Rejuvenating Strokestown’s Potential | 4. Implementation | – | Roscommon County Council |
| Athlone to Ballyleague / Lanesborough Greenway | 1. Strategic Assessment and Preliminary Business Case | – | Department of Transport |
| Lough Key to Carrick-on-Shannon Greenway | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Department of Transport |
| Lough Ree Greenway - Ballyleague/ Lanesborough to Tarmonbarry/ Strokestown/ Roosky | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Department of Transport |
| Boyle Community Library | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Roscommon County Council |
| Slí an Choiste, Monksland | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Department of Housing, Local Government and Heritage |
| Roscommon Town Putting the Spokes back into the Hub- Call 2 - Roscommon Town Centre East Improvement Works | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Roscommon County Council |
| Roscommon Town Putting the Spokes back into the Hub- Call 2 - Roscommon Town Centre West Improvement Works (formerly Activating backlands of Main Street) | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Roscommon County Council |
| Roscommon Town Putting the Spokes back into the Hub- Call 2 - Roscommon Town - Cycle Connectivity Works (formerly Wheel Rim project) | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Roscommon County Council |
| Public Realm Plan - Market Square & Main Street - Covered Civic Space and opening of Historic Well on Market Square | 5. Post Completion Review and Benefits Realisation | – | Roscommon County Council |
| Public Realm Plan - Market Square & Main Street - Enhancement of Laneways and Artistic Installation on Market Square | 4. Implementation | – | Roscommon County Council |
| Rejuvinating Strokestown's Potential | 2. Pre- Tender - Project Design. Planning and Procurement Strategy | – | Roscommon County Council |
Keep exploring
Sources: Uisce Éireann capacity registers; ESB Networks capacity heatmap; National Planning Application Database; DHLGH commencement notices; NDP construction pipeline. Registers are indicative, not connection offers.